UCC – Students Sport Centre Refurbishment

This project included extensive remediation works to existing flood damaged university sports centre completed to extremely demanding deadlines.

 

  • Strip-out of all damaged fit-out works, plant and M&E services
  • Decontamination and sanitisation of all areas
  • Surveys of building elements and components
  • Extensive mechanical and electrical installations including new swimming pool plant and equipment
  • Full fit-out and redecoration of entire complex
  • Intensive construction programme to restore facility to operational status within 12 weeks

Project Team

Client:
University College Cork / Mardyke Leisure Ltd

Architect:
Wilson Architecture

Quantity Surveyor:
AKC

Structural Engineer:
Horgan Lynch Consulting Engineers

M&E Consultant:
JODA Engineering Consultants


Project Details

Contract Value:
€3.0m

Floor Area:    
4,500 sq.m

Duration:
12 weeks