Data Centre – Site Enabling Works

Extensive data centre site works on 28 acres, including bulk earthworks for a 16,000m² Data Hall and Electrical building circa 60,000m3. Also including car parking, a new site access road, internal roadways, sprinkler tank, pump house, water and fuel tanks.

  • Bulk earthworks and disposal for 16,000 m² Data Hall and Electrical building c.60,000 m3
  • Bulk earthworks cut and filling works to roads, car parks
  • 250 RC Pad foundations
  • Pyrite treatment to mudstone and rock exposed in excavations works
  • Full 3D modelling and co-ordination works for utilities installation to predict and avoid services clash
  • External and Internal Utilities installation works including 65,000m high spec fibre optic ducting and large chambers with sealed penetrations using puddle flange and Roxtec adjustable plug
  • HV/MV/LV electrical works including large access chambers with full access removable beam access covers
  • CCTV/ELV/Fire Main/Water Main/PL & ESB Utility installations
  • 5,000m Drainage including up to 750mm diameter pipes with attenuation pond

 

Project Team

Client:
Confidential

Project Manager:
Jacobs Engineering

Architect:
PM Group

Structural Engineer:
PM Group

Services Engineer:
PM Group

Quantity Surveyor:
Jacobs Engineering

 

Project Details

Contract Value:
€ 7.5 Million

Duration:
11 Months