220 Kv Data Centre Substation Phase 1 &2

All civil and building works related to the construction of a 220kv Sub-Station. The finished development consists of two distinct compounds, one to be taken over by Eirgrid and second to be retained by the client.

  • Design and Build contract for Phase1 and Phase 2 of a 220Kv Sub-Station to facilitate a 620,000sq ft Data Centre
  • Civil, structural concrete and building works
  • Overall site area; approx. 22,000m2
  • Two distinct electrical compounds, one operated by Eirgrid as the primary power supplier and second operated by the client to service the Data Centre
  • Phase 2 of the contract maintained the requirement for two distinct electrical compounds.
  • Future expansion capacity incorporated into the design for both the primary power supplier and the Data Centre
  • 3 No. Sub-Station buildings (Eirgrid Control Building, Client Control Building & Diesel Generator Building)
  • Approximately 160 individual concrete plinths of varying sizes to facilitate overhead electrical equipment

 

Project Team

Client:
Gaeltec Utilities Ltd

Engineer:
Jennings O’Donovan

 

Project Details

Contract Value:
€ 7.5 Million

Site Area:
7 Hectares

Duration:
9 months