A95 Ben Aigan - Revised Drainage Works, Scotland
Upgrade works to the A95 Ben Aigan trunk road in Scotland commenced in April 2011. BEAR Scotland awarded John Paul Construction the project which comprises of the removal and upgrading of approximately 1km of drainage to both sides of the A95 trunk road. Existing drainage had previously failed due to land slippage and the approx. 450m section of the A95 was deemed to be at high risk of a landslide. Detailed consultation was undertaken with SEPA regarding environmental management and an extensive traffic management plan implemented for the 20km diversion, allowing the seven week works programme to commence.
LocationScotland
ClientBEAR Scotland/Transport Scotland
EngineerJacobs Engineering
StatusCompleted 2011
Value€0.38m